PROJECT: Brodie Spark Drive, Wolli Creek

LOCATION: Brodie Spark Drive, Wolli Creek NSW 2205

CLIENT: Hutchinson

DESCRIPTION: The second stage of this large project required us to construct retaining structures (a concrete in-situ wall) and conduct bulk excavation, detail excavation, anchoring and dewatering during works. As the bulk excavation was carried out under the water table, we shouldered the risk of general solid waste and any acid sulphate contamination; and because of our experience, the results were per our estimates.

SERVICES PROVIDED: Civil works, bulk excavation, anchoring and remediation.

DURATION: 16 Weeks

VALUE: 6.5 Million