PROJECT: Burwood Plaza

LOCATION: Railway Parade, Burwood NSW 2134

CLIENT: Icon Construction

SERVICES PROVIDED: Demolition, excavation, shoring, anchors, shotcrete, civil works.

DURATION: 14 Weeks

VALUE: 9.1 Million

DESCRIPTION: Provided demolition of existing 5 storey building including basements and carparks of existing shopping centre. Construction for the 6 level basement carpark included completing a full shoring system with shoring piles, foundation piles, ground anchors, rock anchors and shotcrete. The construction of a new vehicle ramp to the existing shopping centre was also developed. Works included all detailed excavation with the constraint of a Sydney water sewer main running through the project.