PROJECT: Australia Towers 2, Sydney Olympic Park
LOCATION: 1 Australia Avenue , Olympic Park NSW 2127
CLIENT: Parkview
DESCRIPTION: The project required piling, bulk excavation (96,000m3), temporary anchoring and shotcreting. The project boundary was along a live railway track which meant we had to take extra precautionary measures to obtain Rail Corp approval.
SERVICES PROVIDED: Excavation, anchoring & shotcreting.
DURATION: 16 Weeks
VALUE: 7.1 Million