PROJECT ADDRESS

Warriewood Waste Water Treatment Plant.

CLIENT

johnholland_03

DESCRIPTION

In this project bulk excavation was required for clarifiers as well as treatment of acid sulphate soil whilst an access road was constructed and storm water drainage provided. The soil was successfully treated with 7% lime to bring it to acceptable levels and this was then recycled as fill material used onsite, saving labour and costs.

SERVICES PROVIDED:
Excavation, civil works and remediation.